Customer: Altra Nebraska, LLC
Location: Carleton, NE
EPC Contractor: Gemma Power Systems, LLC
Design Engineer: Delta-T Corp. / Ford Bacon & Davis
Process Engineer: Delta-T Corp.
The Carleton Ethanol Facility has the capability of producing over 100 million gallons per year of fuel-grade anhydrous ethanol from corn and dry distillers grains with solubles (DDGS) as a co-product, using a dry mill process.
Gemma’s scope included the complete engineering, procurement, construction and start-up of the facility. Project construction was suspended in November 2007 at sixty percent completion.