| The Vandolah power project is a peaking plant consisting of four General Electric 7-FA, dual fuel combustion turbines.
Gemma's EPC scope of work included complete plant design, site development, equipment installation, fuel off-loading and storage facilities, administrative building, electrical interconnection, start-up, commissioning and performance testing.
Construction began in June 2001 and substantial completion was achieved in May 2002. |