SIMPLE CYCLE COMBINED CYCLE BIOMASS
ETHANOL BIODIESEL
Return to Home
Main Portfolio
Simple Cycle Solution

Simple cycle combustion turbine based power generating facilities utilizes combustion turbines as the sole driver for rotating the generator. Rather than recovering the thermal energy from the turbine exhaust, the exhaust is released to the atmosphere via an exhaust stack. Simple cycle facilities require a much shorter construction schedule and require significantly less balance of plant equipment, thus reducing initial plant capital and operational costs. The down side to this configuration is a much less efficient thermal cycle resulting in a higher per MW output cost. The benefit of a simple cycle facility is its ability to come on-line and shut down very quickly. Simple cycle facilities are typically used only during peak, or high demand, periods and may remain dormant for much of the balance of the day.





CPV Sentinal Energy Project
CPV Sentinal Energy Project
The CPV Sentinel Energy Project (CPVS) is being permitted as a nominally rated 850 megawatt (MW) electrical generating facility based on eight natural gas-fired General Electric (GE) LMS100 combustion turbine generators (CTGs) operating in simple cycle mode. The project will supply quick-start peaking capacity, energy, and ancillary services into the California Independent System Operator’s (CAISO) Los Angeles Basin Local Capacity Requirement (LCR) Area. The plant will be equipped with Selective Catalytic Reduction (SCR) and Carbon Monoxide (CO) equipment to reduce plant emissions of NOx and CO. In addition plant will utilize a Zero Liquid Discharge System to eliminate all liquid waste water discharge from the site.

The Project will be built by in a continuous fashion with Phase 1 consisting of the first five units and Phase 2 consisting of three additional units. Construction of the Project is expected to occur during a 26 month period (from February 2009 to April 2011). Operation of the first five turbine units is planned to begin by July 31, 2010 and Phase 2 by April 10, 2011.



A.L. Pierce Re-powering Project
A.L. Pierce Repowering Project
The CMEEC A.L. Pierce Re-powering Project consists of one simple cycle General Electric 7EA combustion turbine relocated to an existing building after four years of storage. Due to the plant’s location in a residential neighborhood, the design incorporated sound walls, acoustically treated equipment and building modifications to meet State mandated noise levels. In addition minimum impact was imposed upon the building while maintaining its original façade concept while the combustion turbine was installed inside the building. These steps have permitted the operation of a power plant in close proximity to residents without visual and environmental impacts.
Gemma’s scope of work included complete plant design, site demolition, development, owner supplied equipment remediation, equipment installation, existing building enhancements, 115 kV switchyard erection, installation of a 115 kV underground power cable system, electrical interconnection, construction of a remote 250,000 gallon fuel oil storage tank with underground transfer system, facility, start-up and commissioning.
Demolition began in late October 2006 and Substantial Completion was achieved in October 2007.
Vandolah Power Project
Vandolah Power Project
The Vandolah Power Project is a 640 mw peaking plant consisting of four (4) General Electric 7-FA, dual fuel combustion turbines operating in simple cycle.
Gemma’s scope of work included complete plant design, site development, equipment installation, fuel off-loading and storage facilities, administrative building, electrical interconnection, start-up, commissioning and performance testing.
Construction began in June 2001 and substantial completion was achieved in May 2002.
DeSoto County Power Project
DeSoto County Power Project
The DeSoto County power project is a 300 MW peaking plant consisting of two General Electric 7FA, dual fuel combustion turbines equipped with inlet fogging systems for power enhancement.
Gemma’s scope of work included engineering, procurement, construction, start-up, commissioning and performance testing of the facility including the 230kV switchyard, fuel off-loading and storage facilities, administrative and maintenance building, and electrical interconnect.
Construction began in July 2001 and substantial completion was achieved in April 2002.
Indigo Energy Facility
Indigo Energy Facility
The Indigo Energy Facility is a peaking plant consisting of three General Electric LM-6000 combustion turbines equipped with SCR systems for emissions controls.
Gemma's scope included project development support, engineering, balance of plant procurement, construction, commissioning and testing of the 135 MW facility, 115kV switchyard and interconnection to Southern California Edison's 115kV grid. Gemma's management and craft personnel successfully executed an aggressive four month schedule with the first two units ready for operation in July 2001 becoming the first of the two (Larkspur being the second) California emergency peaker projects to go online in response to Governor Gray Davis' Executive Orders D-26-01 (Feb. 8, 2001) and D-28-01 (Mar. 7, 2001).
Construction began in April 2001 and substantial completion of the first two of three units was achieved on July 25, 2001.



Larkspur Energy Facility
Larkspur Energy Facility
The Larkspur Energy Facility is a peaking plant consisting of two General Electric LM-6000 cmbusiont turbines (one dual fuel unit and one single fuel unit)equipped with SCR systems for emissions control.
Gemma's scope included project development support, engineering, balance of plant procurement, construction, commissioning and testing of the 90 MW facility, 69kV switchyard and interconnection to San Diego Gas & Electric's 69kV grid. Gemma's management and craft personnel successfully executed an aggressive 4-month design, procurement, construction and commissioning schedule with the facility ready for operation in July 2001 becoming the first of the two (Indigo being the second) California emergency peaker projects to go online in response to Governor Gray Davis' Executive Orders D-26-01 (Feb. 8, 2001) and D-28-01 (Mar. 7, 2001).
Construction began in April 2001 and substantial completion was achieved on July 13, 2001.



Richmond County Phase I Power Project
Richmond County Phase I Power Project
Richmond County Phase I power project is a peaking plant consisting of four General Electric 7FA, dual fuel combustion turbines equipped with evaporative inlet cooling systems for power enhancement.
Gemma's scope encompassed all construction activities associated with the plant; included foundation installation, underground piping and electrical work, heavy hauling, equipment installation, all mechanical and electrical work through interconnection, start-up and commissioning.
Construction began in October 2000 and mechanical completion of the fourth unit occurred on April 30, 2001.



Monroe Power Project
Monroe Power Project
The Monroe power project is a 320 MW peaking plant consisting of two Westinghouse 501 F dual fuel combustion turbines along with fuel off-loading and storage facilities, administrative building and electrical interconnection.
Gemma's scope included the inspection, preparation and shipment of the first turbine from a third party storage location, complete engineering, procurement, construction, commissioning, testing and operation of the power generating facility, fuel-oil off loading and storage facilities, administrative building, and utility interconnect.
Project implementation took place in two phases the first was executed in 4 ½ months during 1999 and the second in 2001.



Richland Peaking Project
Richland Peaking Project
The Richland Peaking Project is a 375 MW facility utilizing three (3) ABB 11N2 simple cycle combustion turbines operating in a simple cycle configuration.
Gemma's EPC scope of work included engineering, site development, procurement, construction, start-up and testing of the power generating facility, fuel-oil off loading and storage facilities, administrative building, and utility interconnect.
Construction began in December 1999. The first two units were completed in May/June 2000 and substantial completion of the entire project was achieved on schedule in November 2000.
Rocky Road Unit No. 4 Power Project
Rocky Road
Rocky Road Unit No. 4 is a Westinghouse 501 D simple cycle peaking plant.
Gemma's scope of work included plant design, site development, equipment installation, and electrical interconnection.
Construction began in December 1999 and substantial completion was achieved in June 2000.
Broad River Energy Center
Broad River Energy Center
The Broad River Energy Center is a 500MWpower generating facility consisting of three General Electric 7-FA simple cycle combustion turbines.
Gemma's scope of work included the interface and final design support with the engineer, the installation of foundations, underground mechanical and electrical work, heavy hauling, equipment installation, and all mechanical and electrical work through interconnection as well as the start-up and commissioning of the plant.
Construction began in December 1999 and mechanical completion was achieved in early May 2000.