Combined cycle combustion turbine based power generating facilities utilize a combination of combustion and steam turbines coupled to independent, or combined generators, to improve efficiencies over a typical simple cycle combustion turbine based facility. A heat recovery steam generator (HRSG) is used to recover the heat from the combustion turbine exhaust and generate steam to a steam turbine thus maximizing plant output by more efficiently utilizing the available thermal energy.
Colusa Generating Station
- Customer: Pacific Gas & Electric Company
- Location: Maxwell, California
- EPC Contractor: Gemma Power Systems, LLC
- Design Engineer: WorleyParsons Group, Inc.
The Colusa Generation station is a 640MW duct fired combined cycle plant using GE frame 7FA combustion turbines and GE reheat steam turbine. The plant incorporates a air cooled condenser and a zero liquid discharge waste water treatment system.
The plant design began in November of 2007 and the project completion is scheduled for August 2010.
Roseville Energy Park
- Customer: Roseville Electric
- Location: Roseville, California
- EPC Contractor: Gemma Power Systems, LLC
- Design Engineer: Worley Parsons Energy Group
The Roseville Energy Park project is a 160 MW combined-cycle power generating facility based upon an SWPC power island consisting of two Siemens Westinghouse SGT-800 turbines, duct-fired, two pressure non-reheat HRSG's and a non-reheat axial exhaust steam turbine. The project also includes a Zero Liquid Discharge system for processing of plant wastewater as well as generation of demineralized water.
Gemma's EPC scope of work includes complete plant design, equipment procurement, construction and start-up/commissioning responsibility.Construction began in August 2005 with Substantial Completion achieved in October 2007.
Hines PB-2 Power Project
- Customer: Progress Energy
- Location: Bartow, Florida
- EPC Contractor: Gemma Power Systems, LLC
- Design Engineer: Parsons Energy & Chemicals
The Hines Power Block II project is a combined cycle plant based upon an SWPC power island consisting of two Siemens Westinghouse 501-F combustion turbines, Vogt-NEM HRSGs, and Siemens steam turbine generator.
Gemma’s EPC scope of work included complete plant design and construction from site development through substation and electrical interconnection. The plant used a cooling pond as a feed to the STG condenser.
Construction began in February 2002 and commercial operation was achieved in December 2003.
Rowan County Power Project
- Customer: Rowan County Power, LLC a Progress Energy company
- Location: Salisbury, North Carolina
- EPC Contractor: Gemma Power Systems, LLC
- Design Engineer: Parsons Energy & Chemicals
The Rowan County power project is a 525 MW two on one combined cycle power island.
The combustion turbines are General Electric 7-FA units. The HRSGs were supplied by
Nooter/Eriksen and the 190 MW steam turbine was supplied by Toshiba.
Gemma's EPC scope of work included complete plant design and construction from site
development through electrical interconnection and initial plant operations.
Construction began in November 2001 and commercial operation was achieved in May 2003.
2003.
Effingham County Power Project
- Customer: Effingham County Power, LLC a Progress Energy Company
- Location: Rincon, Georgia
- EPC Contractor: Gemma Power Systems, LLC
- Design Engineer: Parsons Energy & Chemicals
The Effingham County power project is a 525 MW two on one combined cycle power plant.
The combustion turbines are General Electric 7FA units. The HRSGs were supplied by
Nooter/Eriksen and the 190 MW steam turbine was supplied by Toshiba.
Gemma's EPC scope of work included development support, complete plant design and
construction from site development through substation and electrical interconnection and
included the off site gas metering station.
Construction release occurred on February 1, 2002 and commercial operation was
achieved in August 2003.
Richmond County Phase II Power Project
- Customer: Progress Energy
- Location: Hamlet, North Carolina
- EPC Contractor: Gemma Power Systems, LLC
- Design Engineer: Parsons Energy & Chemicals
The Richmond County Phase II power project is a 525 MW two on one combined cycle
power island and a 178 MW simple cycle power island. All three combustion turbines are
General Electric 7-FA units. The HRSGs were supplied by Nooter/Eriksen and the 190 MW
steam turbine was supplied by Toshiba.
Gemma's EPC scope of work included complete plant design and construction from site
development through electrical interconnection.
Construction began in October 2000 and substantial completion was achieved in June
2002.